Contact usFR

Armand-Corbeil High School

Contact us

Project origin

Centre de services scolaire des Affluents | Ponton Guillot | Expansion

Akonovia Mandate

Energy modelling (2020 Climate Change Action Plan, PACC)

Geothermal conductivity test

Commissioning heat pumps

The project involved expanding and replacing the existing heating system at the Armand-Corbeil high school. The objective was to run three (3) energy modelling scenarios for the initial expansion phase, to validate PACC 2020 compliance, and two (2) additional scenarios for the existing building.